community

Voters Reject Data Centers in 40 of 41 Local Ballot Measures on Nov. 3

Voters in ten states rejected new data center development in 40 of 41 local ballot measures on November 3, in what trackers call the largest such wave on record.

From Our Desk

City of Eagan sues data center company Eagan Capital over "temporary chillers"

The suit is about a data center project in Eagan and a dispute over temporary cooling equipment. It points to a local conflict over how the project is being operated, and it may have implications for municipal oversight or approvals, but the excerpt does not say what relief the city seeks or whether the equipment affects power, water, or land use specifically.

Tax abatements & incentives

Data center limits, minimum wage hike and Medicaid expansion open bill filing for a divided Texas Legislature

The piece is about bill filing in the Texas Legislature, with data center limits among the early measures being filed. It does not say which projects, sites, or companies would be affected, or what any specific limit would require.

Tax abatements & incentives

Potawatomi tribe seeks to expand its small Milwaukee data center - Milwaukee Journal Sentinel

The story is about a proposed expansion of a small data center in Milwaukee by the Potawatomi tribe. Based on the headline and excerpt, it does not say what the project would commit the host to in power, water, tax, or land terms, or whether any approvals or financing details have been filed.

Moratoriums & opposition

Data Centers Work: New group launches to fight misinformation about 'responsible, secure, American' industry

A new advocacy group is trying to counter criticism of data centers and frame the industry as secure and American-made. The excerpt does not identify a specific project, site, utility deal, or local approval, so it does not say what any host community is actually taking on.

Water & cooling

money

JLARC: Data center sales tax break cost state $4 billion over 5 years

This piece says Virginia's data center sales tax break has reduced state revenue by a large amount over five years. It is about public money given up to support data centers, not about a specific new site or build decision.

Tax abatements & incentives

Wyoming Lawmakers Advance Bill To Invest Data Center Taxes For WYDOT

Wyoming lawmakers advanced a bill that would direct tax revenue tied to data centers toward WYDOT. The filing does not say which projects would pay, how much money is involved, or whether the measure would change any specific site deal.

State policy & legislation

Gov. Kotek says data center rules, universal preschool among priorities for next 4 years

The piece says Oregon Gov. Tina Kotek wants new rules for data centers as part of her next four years in office. On the excerpt provided, it does not say what those rules would require, whether they would affect a specific project, or any tax, power, water, or land commitment tied to a named site.

Tax abatements & incentives

power

Congress’s Permitting Bill Is a ‘Massive Giveaway’ to the AI Data Center Industry, Critics Warn

The piece is about federal permitting legislation and how critics say it would ease development conditions for AI data centers. It points to policy changes that could affect where and how projects get approved, but the excerpt does not name a specific site, project, or financial commitment.

State policy & legislation

environment

Project Jupiter air permit hearing postponed; no new date set - KDBC

The air permit hearing for Project Jupiter was postponed, and the filing says there is no new date yet. That leaves the project in the regulatory process without a new hearing schedule, and the excerpt does not say why the hearing was delayed or what the permit covers in detail.